Permits are the schedule, not the paperwork
The single biggest driver on the timeline of a home addition or ADU is the permit and plan check window. Depending on the city, plan check for an addition can take weeks to months, and every correction extends that. We build that time into the calendar up front rather than treat it as a surprise, and we manage the plan check corrections with the city so the file moves rather than sits.
Once permits issue, the build itself runs in phases the city inspects: foundation, framing, rough plumbing and electrical, insulation, drywall, and final. Each phase is scheduled around an inspection. We coordinate those inspections so trades are on site when they should be, not sitting waiting.